Permits set the pace of every new home in Manhattan Beach and Hermosa Beach. Planning review, coastal approvals, and plan check can take longer than framing. Knowing the steps before you design saves months.

This guide covers how the process works in each city and how to look up permit records on a property you own or plan to buy. City procedures change, so confirm current requirements with each city before you submit.

The permit path for a new home

  1. Zoning and feasibility review
  2. Planning review and, if the lot is in the Coastal Zone, a coastal development permit
  3. Building plan check
  4. Demolition permit and air district asbestos notification
  5. Permit issuance and fees
  6. Inspections through final

Step 1: Check zoning before you design

Zoning sets what you can build: height, setbacks, lot coverage, floor area, and parking. Rules vary by zone and neighborhood. A walk street lot in Hermosa Beach has different limits than a lot in the Manhattan Beach Hill Section. Review zoning before you commit to a design, and ideally before you buy. Our free lot report is a good place to start.

Step 2: Planning and coastal review

Manhattan Beach

Manhattan Beach issues its own Coastal Development Permits under the Manhattan Beach Local Coastal Program. The city splits its Coastal Zone into appealable and non-appealable areas. The city's GIS map shows which applies to a parcel. Projects in the appealable area can be appealed to the California Coastal Commission. Neighbors within at least 100 feet receive notice, which adds time to the schedule.

Hermosa Beach

About 43 percent of Hermosa Beach sits in the Coastal Zone. Per the city's current guidance, Hermosa Beach does not yet have a fully certified Local Coastal Program. The city approves projects in concept, and the California Coastal Commission's South Coast District issues the Coastal Development Permit. Build that extra agency into your timeline.

Hermosa Beach also offers a Preliminary Planning Review. It routes plans only to Planning for one round of comments at a reduced fee. It is a useful way to test a design before full plan check.

Step 3: Building plan check

Manhattan Beach

Manhattan Beach takes applications through its Citizen Self-Service Portal. You upload plans as PDFs. The city wants the construction plans combined into one PDF, with structural calculations, energy reports, and soils reports uploaded as separate files. After the permit issues, you download the approved plans from the portal. A printed, stamped set must stay on the job site for inspections.

Hermosa Beach

Hermosa Beach accepts submittals by email to the Community Development Department, or in person on a USB drive for large plan sets. Files must be flattened PDFs. The city calculates plan check fees after it receives the application, and you pay before review starts. Planning, Building, and Public Works review the plans at the same time. Each resubmittal needs a written response and clearly marked revisions.

What slows plan check down

  • Missing or incomplete structural calculations or soils reports
  • Title 24 energy documents that do not match the plans
  • Comments from a prior round left unanswered
  • Design changes made in the middle of review

Each round of corrections can cost weeks. A complete first submittal is the fastest path to a permit.

Modern three-story new construction home in Hermosa Beach with a gray exterior, built by Levine Homes Real Estate and Construction

Step 4: Demolition and the asbestos notification

Most South Bay custom homes replace an existing house. Before demolition, South Coast AQMD Rule 1403 requires an asbestos survey by a Certified Asbestos Consultant. It also requires an electronic notification at least 10 working days before demolition starts. The notice applies even when the owner believes the house has no asbestos. State law bars a city from issuing a demolition permit until it receives a copy of that notification. Schedule the survey early.

Step 5: Inspections through final

Once the permit issues, city inspectors sign off each stage of the work: foundation, framing, rough electrical, plumbing, and mechanical, insulation, drywall, and final. A failed inspection costs days. Keep the stamped plans on site and book inspections ahead.

How to look up permit records for a property

Buying an older home or a teardown lot? Permit history shows what the city approved, what was built without permits, and what past owners changed.

In Manhattan Beach, request building permit records through the city's online public records request system. Include the property address and the date range you need. To review or copy plans, the city also requires a Building Plan Review and Copy Request through Community Development.

In Hermosa Beach, contact the Community Development Department for the permit history on an address.

As a licensed real estate broker, we review permit history on properties our clients plan to buy. See our questions to ask before buying a fixer-upper for more.

Frequently asked questions

Who issues coastal development permits in Manhattan Beach?

Manhattan Beach issues its own Coastal Development Permits under its Local Coastal Program. Projects in the appealable area can be appealed to the California Coastal Commission, and neighbors within at least 100 feet receive notice.

Who issues coastal development permits in Hermosa Beach?

Hermosa Beach does not yet have a fully certified Local Coastal Program. The city approves projects in concept, and the California Coastal Commission’s South Coast District issues the Coastal Development Permit.

How do I submit plans for building plan check?

Manhattan Beach takes applications through its Citizen Self-Service Portal as PDF uploads. Hermosa Beach accepts flattened PDFs by email to the Community Development Department, or in person on a USB drive for large plan sets.

Do I need an asbestos survey before demolition?

Yes. South Coast AQMD Rule 1403 requires an asbestos survey by a Certified Asbestos Consultant and an electronic notification at least 10 working days before demolition starts. A city cannot issue a demolition permit until it receives a copy of that notification.

How do I look up permit records on a property?

In Manhattan Beach, request building permit records through the city’s online public records request system. In Hermosa Beach, contact the Community Development Department for the permit history on an address.

Why your builder matters in the permit process

Permits are where local experience pays off. We build in Manhattan Beach and Hermosa Beach regularly, and our like-for-like build times run well below each city's average. See the data for Manhattan Beach and Hermosa Beach.

Plan your Manhattan Beach or Hermosa Beach new construction

Planning Hermosa Beach new construction or a custom home in Manhattan Beach? Contact Levine Homes Real Estate and Construction to review your lot and permit path before you design.